US 380 Tracker

US 380 is the big east-west highway just north of Lowry Crossing. This tracker covers the Texas segments most relevant to us — roughly McKinney through Princeton — including the widening project, the proposed bypass, and connecting projects like Spur 399.

Get an alert whenever there's news on this project.

US 380 Widening (Airport Drive to CR 458)

TxDOT project widening US 380 from four to six lanes through the McKinney–Princeton area.

Where it stands

StudyUnder constructionComplete

Crews are widening US 380 from four to six lanes. As of May 2026 the work was about 25% complete, with completion targeted for the end of 2028. Collin County contributed $11 million toward the project in December 2023.

Lead agency

TxDOT

Limits

Airport Drive → CR 458

Funding

Funded; under construction

Expected completion

End of 2028

What it means for Lowry Crossing

US 380 is the main east-west highway just north of Lowry Crossing. More lanes should ease daily congestion, but expect lane shifts and slowdowns through 2028.

Next milestone

Construction continues toward end-of-2028 completion

Last verified: Sep 25, 2026

Timeline

Under construction

US 380 widening about 25% complete, targeting end of 2028

By May 2026 the US 380 widening was roughly a quarter finished, with TxDOT targeting completion at the end of 2028. Drivers should expect continued lane shifts through the corridor.

Why it matters: This is the stretch of US 380 most Lowry Crossing residents drive; knowing the timeline helps set expectations for the daily commute.

Approved

Collin County commits $11 million to the US 380 widening

Collin County agreed to contribute $11 million toward widening US 380, helping move the project forward through the McKinney–Princeton corridor.

Why it matters: Local funding helps keep a state highway project on schedule — a signal the widening near Lowry Crossing was advancing.

Source: Collin CountyOfficial source

US 380 Princeton Bypass

TxDOT plan for a new controlled-access freeway routing US 380 north around Princeton.

Where it stands

StudyRight-of-wayComplete

TxDOT plans a new limited-access freeway (ultimately up to eight lanes, about 11.8 miles) that would carry US 380 north of downtown Princeton. TxDOT issued its environmental clearance (a FONSI) on January 6, 2025 and began anticipating right-of-way in 2025. A construction letting is estimated around 2027, pending funding.

Lead agency

TxDOT

Limits

West of Princeton → East of Princeton

Length

About 11.8 miles

Funding

Not yet fully funded for construction

Expected completion

No date announced

What it means for Lowry Crossing

Routing through traffic north of Princeton could take pressure off the existing US 380 near Lowry Crossing over the long term, but this is a large, multi-year project still in the right-of-way stage.

Next milestone

Right-of-way acquisition; letting estimated ~2027

Last verified: Sep 25, 2026

Timeline

Approved

TxDOT issues environmental clearance for the Princeton bypass

TxDOT issued a Finding of No Significant Impact (FONSI) on January 6, 2025, clearing the environmental step for a new US 380 freeway routed north of Princeton. Right-of-way work was anticipated to begin in 2025, with a construction letting estimated around 2027 pending funding.

Why it matters: Environmental clearance is a major milestone — it lets TxDOT start buying land, though a funded build date is still years away.

Spur 399 Extension

TxDOT project widening Spur 399 and extending it to US 380, with a planned FM 546 interchange.

Where it stands

StudyUnder constructionComplete

Segment 1 widening has been under construction since June 2025 (built by Webber, about $157.4 million). A larger extension would carry Spur 399 as a freeway to US 380 with a planned interchange at FM 546. That extension is estimated at roughly $967–983 million and is not yet scheduled.

Lead agency

TxDOT

Limits

US 75 → US 380

Estimated cost

Extension about $967–983 million

Funding

Segment 1 funded; full extension not scheduled

Expected completion

No date announced

What it means for Lowry Crossing

A planned FM 546 interchange would connect Spur 399 directly to the road that runs through Lowry Crossing, which could reshape regional traffic for years to come.

Next milestone

Segment 1 construction continues

Last verified: Sep 25, 2026

Timeline

Under construction

Spur 399 Segment 1 widening begins construction

Construction on the first segment of the Spur 399 widening began in June 2025, built by Webber under a contract of about $157.4 million.

Why it matters: This is the first concrete step in a much larger plan that could eventually connect Spur 399 to US 380 with an interchange at FM 546.

Proposed

A ~$1B plan would extend Spur 399 to US 380

TxDOT’s longer-range plan would extend Spur 399 as a freeway around McKinney to US 380, including a planned interchange at FM 546. The extension is estimated at close to $1 billion and is not yet scheduled.

Why it matters: A future FM 546 interchange would tie a major freeway directly to the road running through Lowry Crossing — worth watching even though it is years away.

US 380 at Beauchamp Boulevard

Intersection rebuild where US 380 meets Beauchamp Boulevard in Princeton.

Where it stands

StudyUnder constructionComplete

Work to rebuild the US 380 and Beauchamp Boulevard intersection began October 5, 2025 and is expected to take about two and a half years.

Lead agency

City of Princeton / TxDOT

Limits

US 380 at Beauchamp Blvd → ?

Funding

Under construction

Expected completion

About 2.5 years (began Oct 2025)

What it means for Lowry Crossing

This is a nearby US 380 intersection Lowry Crossing drivers pass through toward Princeton; expect lane closures and delays during construction.

Next milestone

Construction continues

Last verified: Sep 25, 2026

Timeline

Under construction

Intersection rebuild begins at US 380 and Beauchamp Boulevard

Work to rebuild the US 380 and Beauchamp Boulevard intersection in Princeton began October 5, 2025 and is expected to take about two and a half years.

Why it matters: Lowry Crossing drivers heading into Princeton pass through this intersection, so expect closures and delays during the rebuild.