Highway 380 & Bridgefarmer Corridor

Everything we know about the TXB gas station development, Bridgefarmer Road widening, and activity along US Highway 380 in Lowry Crossing — aggregated from 100 City Council, EDC, and MDD meetings plus regional news sources. Updated automatically as new minutes and news become available.

TXB Development
22
meetings with TXB updates

Gas station & convenience store at Hwy 380 & Bridgefarmer. Development Agreement approved Oct 28, 2025. Targeted open Sept–Oct 2026.

Click to view timeline ↓
Bridgefarmer Rd
83
meetings on road work

Phase II expansion (Settler’s Trail → Highridge Farms) at est. $1.76M, plus Langston Lane culvert repair ($223K vs $437K replace).

Click to view timeline ↓
Hwy 380 Corridor
16
mentions in meetings

BHC engineering services for Bridgefarmer/Hwy 380 intersection approved Oct 14, 2025. Sewer easements secured.

Click to view timeline ↓

Latest News & Regional Updates

As ofMay 15, 2026
active

The 7 Fastest-Growing DFW Suburbs of 2026

The Dallas North Tollway, U.S. 380, U.S. 75, and I-30 are carrying more growth than they were originally built to handle. Residents with hybrid schedules tend to have an easier time adjusting. A lot of the movement is local or regional, not just out-of-state. The popular story is that everyone is moving here from California. Some are, sure. But plenty of buyers are moving from Frisco to Celina, Plano to McKinney, Allen to Anna, or Mesquite and Garland toward Fate and Forney.

As ofMay 15, 2026
upcoming

TxDOT scheduling public meeting for FM 543 widening in McKinney — May 21, 2026

TxDOT has scheduled a virtual public meeting (with in-person option) for May 21, 2026 regarding the FM 543 project from CR 125 to Trinity Falls Parkway in McKinney. FM 543 runs near the Lowry Crossing area and connects to US 380. This suggests active planning for widening or improvements on this corridor.

PublishedMay 14, 2026
active

Council calls runoff, OKs taller buildings on U.S. 380 | Princeton Herald

2026-05-11-02 of the City of Princeton amending Section 82-22 (d) &quot;Height and Area regulations&quot; to <strong>add a height increase within 1,000 feet of US 380 right of way</strong> to this Section of the... read more ...

As ofMay 11, 2026
active

TxDOT Paris Road Work For May 10 – EastTexasRadio.com

<strong>FM 36, desde la US 380 hasta la SH 66.</strong> El proyecto de 6,11 millas rehabilitará la superficie de la carretera y añadirá tratamientos de seguridad en los extremos. La superficie final del pavimento está terminada. El contratista se está preparando para rellenar los bordes.

As ofMay 10, 2026
active

FM 547 rehabilitation (FM 6 to US 380) — 25% complete, finishing October 2026

TxDOT's $16.4 million FM 547 rehabilitation project from FM 6 to US 380 is now 25% complete. Construction began July 2025 and is expected to be completed by October 2026. FM 547 is a key east-west route near Lowry Crossing connecting to US 380.

As ofMay 10, 2026
active

Collin County Northeast Freeway study — preferred alignment expected spring/summer 2026

TxDOT's study for a new 10-mile Collin County Northeast Freeway (CCNEF) connecting SH 121 to the future US 380 freeway is progressing. Public meetings were held Dec 2025–Jan 2026 at Princeton High School. A preferred alignment is expected to be announced in spring or summer 2026. The study anticipates interchanges along SH 121, the Collin County Outer Loop, and US 380.

PublishedMay 10, 2026
active

Spur 399 McKinney expansion under construction — first traffic shifts expected spring 2026

TxDOT broke ground on the Spur 399/SH 5 widening in McKinney in June 2025. The first segment (Stewart Road to Eldorado Parkway) is widening from four to six lanes at a cost of $157 million. First traffic shifts are anticipated for spring 2026, with completion of this segment expected by summer 2029. The larger $1 billion extension to US 380 will be bid in 2026.

As ofMay 10, 2026
upcoming

US 380 Prosper/Frisco freeway conversion — construction starting 2026

TxDOT plans to begin construction in 2026 on the US 380 segment from Teel Parkway to west of Lakewood Drive (Prosper/Frisco area). The 5.9-mile project will widen and convert US 380 into a freeway. This segment connects to the Denton County project nearing completion and will extend the freeway further into Collin County.

Showing 8 of 46 news items. See all on the Regional Updates page.

Timeline — Council & EDC/MDD Discussions

Every mention of TXB, Bridgefarmer Road, or Hwy 380 from official City Council, EDC, and MDD meeting minutes. Tap any card to expand full context.

Mar 24, 2026
City Council
Bridgefarmer RdHighway 380

Bridgefarmer Road

Ask for council’s consideration of use and let park board have a plan and rules. Also, post signage of no portable grills. Ken Bradford, 820 S. Bridgefarmer – There is no name on the Milligan Cemetery. I think there should be and offer to project manage this a...

Mar 10, 2026
City Council
Bridgefarmer Rd

Bridgefarmer Road

8) Public Hearings - None 9) Old Business: A) Discuss, consider, and act on bid for culvert repair at Langston Lane and Bridgefarmer Road. Repair cost is $223K versus replacement at $437K. Eusebio Trujillo moved to table until next budget year; second by Chris Madrid. Motion passed unanimously.

Feb 24, 2026
City Council
Bridgefarmer Rd

Bridgefarmer Road

8) Public Hearings - None 9) Old Business: A) Discuss, consider, and act to select asphalt option for Bridgefarmer Road Phase II. Justin Ivy shared the cost to do Phase II to Highridge Farms Road of $1.763M. Tammy Hodges moved to table for later date after [so...

Feb 10, 2026
City Council
Bridgefarmer RdTXB Development

TXB Development + Bridgefarmer

City Council Meeting Minutes of February 10, 2026 Eusebio confirmed that we are not building/widening the road for TXB, we are doing it for our citizens. Chris confirmed we are planning to upsize the pipes – will have costs in a week. D) Discuss, consider, and...

Feb 3, 2026
EDC/MDD
TXB Development

TXB Development

We asked Tim to put together plans and costs for the Tarana and get back to us. B. Updates: a. Open Infra – We finally got a response on 1/21, but still no timeline. b. TXB project status – Work is proceeding and they would like to open September/October. c. D...

Feb 3, 2026
EDC/MDD
TXB Development

TXB Development

We asked Tim to put together plans and costs for the Tarana and get back to us. B. Updates: a. Open Infra – We finally got a response on 1/21, but still no timeline. b. TXB project status – Work is proceeding and they would like to open September/October. c. D...

Jan 13, 2026
City Council
Bridgefarmer Rd

Bridgefarmer Road

, 1610 Lake Trail Circle – Liked the idea of asking questions after an item was explained. Linda Hilsenbeck, 105 Settlers Trail – Agree about questions after. Mark Shultz, 1115 S. Bridgefarmer – Agree with both, discuss after. 7) Business Items: A) Presentatio...

Jan 6, 2026
EDC/MDD
Bridgefarmer RdHighway 380TXB Development

TXB Development + Bridgefarmer

AT&T call – Chris spoke with them; they thought commercial would run down Bridgefarmer. Not ready for anything else at this time. c. TXB project status – Everything is moving forward with plans and surveys. We do not have a signed Development Agreement in hand...

Dec 9, 2025
City Council
Bridgefarmer RdHighway 380

Bridgefarmer Road

Pete Christian, 325 Overland – Police department; large trucks can’t be pulled over. Clear signs before entering Bridgefarmer. A civil suit takes it out of the city. 7) Recognition of Individuals by Mayor and Council - None 8) Business Items: A) Presentation of the FY2025 Audit by Wayne Nabors.

Dec 2, 2025
EDC/MDD
TXB Development

TXB Development

Chris suggested we check with the Simpson Crossing HOA to see if they have anyone qualified and interested. We could see if someone from TXB has an interest. No action, continue search. B. Updates: a. Open Infra – Janis emailed Kristoffer on 11/25 requesting a...